The drainage and mix train continues to roll through the course at great pace. We have now offically crossed the half way point with the installation of drainage and the mix will cross that point today - with Mother Nature's cooperation. Before the heavy rains came again yesterday, we had begun the drainage process on the 13th and 11th greens. These two greens mark the 10th and 11th greens to go through the drainage process. Having not yet completed three full weeks of the construction schedule, I could not be happier being where we are. Everything continues to point to a third week of August seeding date.
To Date:
Drainage Installed On: 2, 3, 4, 5, 12, 15, 16, and 18 (13 and 11 in process today)
Mix Installed On: 2, 3, 4, 12, 15, 16, 18, (#5 to be done today)
Subgrades: All approved by Tom Doak